The City’s existing Hames Water Reservoir is a 500,000 gallon coated steel tank located off Hames Road in Corralitos. The interior coating is due for maintenance. It was originally constructed in 1969 and the interior coating was previously rehabilitated over 30 years ago. The project will also upgrade the reservoir’s inlet and outlet connections to minimize risk of loss of storage during a seismic event. This project is anticipated to extend the remaining useful life of the reservoir which otherwise is in good condition.

Hames Water Reservoir Interior Coating Project

Project Updates

June 15, 2022: Image 2The contractor has successfully completed the interior coating of the reservoir, and is working with City operations staff to fill and disinfect the reservoir to put it back in service. We would like to thank Top Line Engineers and City water operations and engineering staff for the successful, on-time delivery of this much needed capital improvement project!

April 1, 2022:  Hames reservoir interior rust - March 2022Bids were opened and in January the project was awarded to Top Line Engineers, Inc. in the amount of $407,800. The Contractor mobilized on-site in March and progress on removing the existing interior coating is underway.

 

November 1, 2021: The City has completed the design of the project and will be taking the plans and specifications to Council for acceptance to bid at the November 9, 2021, Council Meeting. The current bid opening date is planned for December 14, 2021, pending Council approval.